Airfield Lighting Installation
Company | Avionics Group |
---|---|
Date | 15.08.2011 |
Avionics are pleased to be appointed Head Contractor for this Project. Sydney Airport are investing $25m, involving the installation of Stop Bar lights at the taxiway entries to the 3 runways, as a major safety initiative to prevent aircraft from inadvertently entering a runway without air traffic control clearance. Construction is scheduled to be completed in mid 2012 and will involve:
- Civil Infrastructure Works (conduits, pits and ducts). Avionics have teamed up with Ford Civil;
- Electrical, airfield lighting installation works, including the installation of multi-deep base canisters;
- Power and Communication Cabling; Control System Installation (1000 smart switches & 50 airfield micro-wave barrier detectors). Avionics have been engaged by ATG Airports UK;
- Final Commissioning (testing and training).
Contact
Unit 6, 10-18 Ocean Street
Botany
Austraila
NSW 2019
- 02 9316 5025