Airport Prefabricated Vehicle Pits

Company Premier Pits
Date 01.10.2014

The project: Installing two working pits and one full MOT pit into a newly built workshop.

 
Pit specification: A 27m working pit with 3x2m equipment recesses linked with a connecting tunnel to a 17.75m VOSA pit which had a 2m equipment recess, shaker plate sumps, a split bed brake tester and an escape tunnel with a vertical ladder.
 
The problem: Extremely difficult ground conditions where 200mm of soil was covering sand which was deeper than the pits. Premier were unaware of this problem.
 
Solution: To use driven sheet piling – 80% of which was later reclaimed.
 
Outcome: Installation took a little longer than was originally estimated. Using conventional pit construction methods would have resulted in many extra days on site. The delighted client now has a smart water tight pit, that is an asset to his operation.