A new passenger terminal building with a gate and underground parking. Also included in this project is a new runway with taxiway, apron extension and facilities such as fuelling.

The gate has seven passenger boarding bridges. The building is served by a central utility plant.

Client
Sofia Airport Project Implementation Unit, Bulgaria

Project Manager
NACO, The Hague, Netherlands

Architect
NACO, The Hague, Netherlands

Structural Engineer
Stroy Consult, Sofia, Bulgaria
NACO, The Hague, Netherlands

Built-up area
50.000 m2

Start design
September 1999

Start construction
March 2003

Completion project
September 2005