ALSTEF has been awarded a contract for the design and installation of the Baggage Handling System at Zagreb Airport
Company | PROAVIA |
---|---|
Date | 12.09.2014 |
CROATIA BRANCH BOUYGUES BATIMENT INTERNATIONAL CROATIA BRANCH
is responsible for the construction of a new terminal at Zagreb Airport, operated since 2013 by the consortium MZLZ formed by BOUYGUES BATIMENT INTERNATIONAL, Aéroports de Paris Management, TAV Airports, and a subsidiary of the World Bank.
The contract awarded to ALSTEF includes:
- the design and installation of one additional check-in island, with a separate screening line within the existing terminal which recently became operational .
- the design and installation of a comprehensive Baggage Handling System including automated baggage handling, hold baggage screening and sorting of bags at arrivals and departures. Two new 15-desk check-in islands (with the option of adding two others ), two “Standard 3” screening lines, an automatic sorter, and four baggage delivery lines.
The works will be completed over a 30 month period, in time for the opening of the new terminal in the last quarter of 2016.