Participated as members of the ORAT team in the preparation of the handover and opening of the new Larnaca International terminal  as Special Systems & Maintenance Specialists (2009).

The Technical Assistance and Consulting services comprised the following:

  • Restructure, optimize and redefine the maintenance and technical contracts to meet the expected level of performance and optimize HERMES Airport’s budget.
  • Define, structure and propose possible maintenance organizations and provide assistance to HERMES Airports choosing the best-suited solution.
  • Ensure set up of storage areas to receive, catalogue, and replenish all spare parts and consumables.
  • Ensure set up and equip maintenance areas and Technical Data Center.
  • To simulate and monitor technical failures during Terminal operation trials.
  • Tender and award outsourced maintenance contracts including Baggage Handling system, Passenger Boarding Bridges, chillers, boilers, lighting, elevators & escalators, fire alarms, sewage and drainage systems.
  • Receive, file and/or store all as built drawings, specifications, operations and maintenance manuals, test certificates, systems training documentation, spare parts, guarantees, warranties.
  • Set up scheduled preventive maintenance plans for the following systems and equipment in accordance with manufacturers recommendations from the relevant operating and maintenance manuals:

        – Baggage systems
        – Passenger boarding bridges, VDGS, GPU and PCA
        – HVAC
        – Lighting
        – Electronic equipment (FIDS, BIDS, intercom, bldg fire-alarm system)
        – Escalators, elevators and moving walkways,
        – Sewage and Drainage systems,
        – Car Parking Management System (CPMS)

 

LARNAKA AIRPORT – DESCRIPTION

  • 7,5 Million Passengers per year
  • 3,217 passengers per hour in peak periods
  • 20 Boarding Gates
  • 16 Passengers Boarding Bridges
  • 67 Check-in Counters
  • 23,210 KVA Electric Power installed
  • 6,200 KW Cooling Power installed
  • 100,000 m2 Terminal Building
  • 9,500 lm Drainage / Sewage Networks
  • 1,360 lm of conveyors in BHS
  • 5 Bag Claim Carousels
  • 2,450 Parking Positions