Dubai Awards AED56.5 Billion in New Contracts for Al Maktoum International Airport


Image credit: Dubai Media Office / Dubai Aviation Engineering Projects (DAEP)
Dubai has awarded new contracts worth approximately AED56.5 billion for the development of Al Maktoum International Airport, marking a major expansion of the construction programme for the emirate’s future global aviation hub.

Announced by H.H. Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, the latest awards bring the total value of contracts and packages awarded for the airport to approximately AED80 billion.

The contracts cover major infrastructure works across the West Terminal Building, Concourses 1, 2, 3 and 4, alongside electrical power infrastructure and associated airport systems.

Construction advances across terminal and concourse facilities

The new packages include substructure and infrastructure works for the West Terminal Building, Concourse 1 and Concourse 4, covering basements, underground tunnels, access ramps, ground transportation facilities and supporting utility networks.

Contracts for Concourses 2 and 3 will advance construction above ground, including structural frameworks, large-span steel roof structures, façades, architectural fit-out, mechanical and electrical installations, and specialist airport systems.

The awards also include the construction of two principal 132/11 kV electrical substations, together with associated cabling and power infrastructure to support the airport’s future buildings and operational facilities.

Major construction progress recorded

Dubai Aviation Engineering Projects confirmed that construction is progressing across passenger terminal areas, concourses, tunnels, transport facilities and utilities.

More than 24.23 million cubic metres of excavation have been completed, alongside over 5.2 million cubic metres of backfilling and the installation of 7,635 piles.

Across the substructure works for Concourses 2 and 3, more than 875,000 cubic metres of concrete have been placed and over 226,000 tonnes of reinforcement steel installed.

The combined workforce across the project packages currently stands at approximately 14,000 personnel, with cumulative working hours exceeding 21.3 million.

The latest contracts will allow construction to advance concurrently across several key areas of Phase One, supporting the coordinated development of passenger facilities, baggage handling systems, underground transportation networks and essential airport infrastructure.

Dubai Aviation Engineering Projects is responsible for the integrated delivery of the development programme, including planning, procurement, construction and operational readiness.